West Sussex County Council – Highway Drainage Improvement Works in Hassocks – 5th July for 9 weeks

Highway drainage improvement works on Keymer Road and Chancellors Park due to begin on the 5th July 2025 for 9 weeks.

The works are extensive and will take place from the railway station through to the junction with Ockley Lane. The works will be phased and take place under a variety of road closures and traffic management systems.

Drainage Works Programme: Keymer Road, Hassocks
Location Traffic Management Date Working Times
Keymer Road, Station Approach West, Hassocks Night Time Road Closure 5 to 20 July 8 pm to 6 am
Keymer Road, Hassocks Two-Way Lights 19 to 27 July 2025 7:30 am to 6 pm
Chancellor Park junction with Keymer Road, Hassocks 24hr Road Closure 28 July to 15 August 2025 6 am to 6 pm
Hassocks Infant School None 15 August to 29 August 2025 6 am to 6 pm
Keymer Road junction with Chancellor Park, Hassocks Multi – Way Lights 28 July to 15 August 2025 9:30 am to 4 pm
Keymer Road extent from Grand Avenue to Oakley Lane, Hassocks Road Closure and

Multi – Way Lights where possible

16 to 29 August 2025 6 am to 6 pm

 

Real-time information for road users, can be viewed on one.network and FAQs are available here: FAQ – Keymer Road Hassocks Drainage Improvement Scheme

Hassocks Parish Council
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.